Pull the business side (Kelly) into the FIPS 6.18 CAVP-retrigger vs fork call
Situation
Justin flagged that upstream 6.18 LT landed hundreds of CVEs/fixes touching the crypto code being FIPS-certified, forcing a choice between re-triggering CAVP (risking the 8/8 Google delivery) or forking/reverting the kernel (a growing maintenance burden). Justin was inclined to retrigger CAVP and risk the timeline. Peter did not make the technical call himself - he decided the business side must be convened, with Kelly Hall involved, because the choice puts the Google 8/8 delivery at risk.
Reasoning
Retrigger-vs-fork is genuinely Justin technical call, and Peter signaled he backs it (perfect). But the consequence - slipping 8/8 for Google - is a business/contract decision that cannot be made inside engineering. So Peter convenes Kelly, who owns the Google relationship, rather than let engineering absorb a timeline-risk decision that is not theirs. Consistent with how Peter is handling all of Google now: engineering owns the technical right answer, business owns the timeline/commercial trade-off.
Additional Context
Peter confirmed the framing. Attribution guardrail: the loggable Peter decision is convening the business side, NOT the CAVP-retrigger call itself (that is Justin). Justin noted this will recur over 6.18 life, so this establishes the escalation path. ESV cert also slipping, compounding 8/8 risk.
Observed Evidence
Justin: inclined to retrigger CAVP and risk the timeline. Peter: We need to pull the business side together for a conversation on this. Kelly should be involved. perfect. please let me know if there are any questions.
Confidence Breakdown
Reasoning Depth Analysis
People Involved
Source
reflection
AI Confidence
82%
Related Context
slack
Justin: I am inclined to retrigger CAVP and risk the timeline rather than forking or reverting. Peter: We need to pull the business side together for a conversation on this. Kelly should be involved.
Outcome
Business side is engaged and the deliverable is moving - Kelly Hall relayed the Google agreement closure on 2026-07-30 and CLK 6.18 FIPS for Google is Core Distro top priority, IN PROGRESS at 70 percent confidence.
Rating: 4/5
Decision ID: 3340f800-1b32-4afe-b62e-4a163b227363